Thursday, January 18, 2007

Didier has met the window man and they have measured up correctly (as the doors and windows have changed a bit since they were quoted). Window man is now ordering the windows and doors at the correct size (definitive quote on its way). They'll be delivered in 3 weeks and will take a week to fit. We wont have to pay for them until March. In the meantime the water pipes will be completed and the under floor heating pipes laid. They are also knocking down the fireplace wall and replacing that, and also completing the columbage whilst the doors are on order.

Didier is sending me an updated electricity plan this week as he thinks he has some better ideas than the ones I sent him (he's probably right)

After the doors and windows are in (mid feb) they will start on the partition walls, then can do the tiling in march.

Once the tiles are down they can do the plastering and painting and fit the bathroom furniture etc. He reckons we are on for mid to end of May for all works.